Pre-loader

Consultancy Projects

Sl Title Client Organisation PIs
1 Scientific study of West Kenda OCP of New Kenda colliery, Kenda Area, ECL as per regulation no. 138(1) and 37(2) c of CMR-2017, proposal for dealing/ sealing of fire in the developed galleries of disused working of R-Vl seam and stabilization of ground in the pot hole/ subsided area Eastern Coalfields Limited (ECL) PI: Prof. (HAG) N. C Dey
Consultants: Dr. Dipankana Bhattacherjee
2 Scientific monitoring of dump and pit slope stability by determining FOS and pore pressure at Basantimata Dahibari Colliery under CV area of BCCL Bharat Coking Coal Limited PI: Prof. (HAG) N. C Dey
Consultants: Dr. Dipankana Bhattacherjee
3 Preparation of Geotechnical report on Highwall mining at Amalgamated Amlo Dhori MINSOL Limited PI: Prof. (HAG) N.C Dey
Consultants: Dr. Dipankana Bhattacherjee
4 Widening/ Improvement to 4 (Four) Lane with Paved Shoulder of existing single lane from Srirampur (near Bhairiguri village) to Kachukhana Harichara Paglagaunj Section (PKG -I) of Srirampur to Dhubri Road of newly declared NH-127B of existing KM 0.000 to KM28.050 (Design KM. 0.000 to KM. 27.650), (Design Length= 27.650km) on EPC Bas is in the state of Assam under JICA Simplex Infrastructures Limited PI: Prof. Tapas K Roy
Consultants: Dr. Sujit Kumar Dalui and Dr. Dipankana Bhattacherjee
5 Scientific Study for determining the Safe Method of Working, Ultimate Pit Slope and Dump Slope with Monitoring of Slope Stability of Basantimata- Dahibari Colliery Under CV AREA-XII, BCCL. Bharat Coking Coal Limited PI: Prof. (HAG) N. C Dey
Consultants: Dr. Dipankana Bhattacherjee
6 Widening to 2 (Two) Lane with Paved shoulder of Imphal to Jiribam section of NH37 from Design Chainage 66.110 km to 101.280 Km (Existing Chainage km 67.496 to Km 103.557) (PKG-4) in the State of Manipur on Engineering, Procurement & Construction (EPC) mode, BLAPPL-GPPL (Joint Venture) PI: Prof. Tapas K Roy

Created: 23 November 2019