Sl | Title | Client Organisation | PIs |
---|---|---|---|
1 | Scientific study of West Kenda OCP of New Kenda colliery, Kenda Area, ECL as per regulation no. 138(1) and 37(2) c of CMR-2017, proposal for dealing/ sealing of fire in the developed galleries of disused working of R-Vl seam and stabilization of ground in the pot hole/ subsided area | Eastern Coalfields Limited (ECL) |
PI: Prof. (HAG) N. C Dey Consultants: Dr. Saptarshi Kundu |
2 | Scientific monitoring of dump and pit slope stability by determining FOS and pore pressure at Basantimata Dahibari Colliery under CV area of BCCL | Bharat Coking Coal Limited |
PI: Prof. Netai Chandra Dey Consultants: Dr. Saptarshi Kundu |
3 | Preparation of Geotechnical report on Highwall mining at Amalgamated Amlo Dhori | Minsol India Private Limited |
PI: Prof. Netai Chandra Dey Consultants: Dr. Saptarshi Kundu |
4 | Widening/ Improvement to 4 (Four) Lane with Paved Shoulder of existing single lane from Srirampur (near Bhairiguri village) to Kachukhana Harichara Paglagaunj Section (PKG -I) of Srirampur to Dhubri Road of newly declared NH-127B of existing KM 0.000 to KM28.050 (Design KM. 0.000 to KM. 27.650), (Design Length= 27.650km) on EPC Bas is in the state of Assam under JICA | Simplex Infrastructures Limited |
PI: Prof. Tapas K Roy Consultants: Dr. Sujit Kumar Dalui and Dr. Saptarshi Kundu |
5 | Scientific Study for determining the Safe Method of Working, Ultimate Pit Slope and Dump Slope with Monitoring of Slope Stability of Basantimata- Dahibari Colliery Under CV AREA-XII, BCCL. | Bharat Coking Coal Limited |
PI: Prof. Netai Chandra Dey Consultants: Dr. Saptarshi Kundu |
6 | Widening and Up-gradation 2-Lane with paved shoulder configuration and geometric improvements from km 208.00 to km 250.00 (Package 5) on Aizawl - Tuipang section of NH-54 in the state of Mizoram | ABCI Infrastructures Pvt. Ltd. under National Highway & Infrastructure Development Corporation Ltd. |
PI: Prof. Tapas K Roy |
7 | Widening to 2 (Two) Lane with Paved shoulder of Imphal to Jiribam section of NH37 from Design Chainage 66.110 km to 101.280 Km (Existing Chainage km 67.496 to Km 103.557) (PKG-4) in the State of Manipur on Engineering, Procurement & Construction (EPC) mode | BLAPPL-GPPL (Joint Venture) under National Highway & Infrastructure Development Corporation Ltd. |
PI: Prof. Tapas K Roy |
8 | Widening and Up-gradation 2-Lane with paved shoulder configuration and geometric improvements from km 166.00 to km 208.00 (Package 4) on Aizawl - Tuipang section of NH-54 in the state of Mizoram | ABCI Infrastructures Pvt. Ltd. under National Highway & Infrastructure Development Corporation Ltd. |
PI: Prof. Tapas K Roy Consultants: Dr. Dipankana Bhattacherjee |
Created: 23 November 2019